SOLUTION: if it takes 4 men to build a shed in 9 hours, how long will it take 6 men?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: if it takes 4 men to build a shed in 9 hours, how long will it take 6 men?      Log On


   



Question 783441: if it takes 4 men to build a shed in 9 hours, how long will it take 6 men?
Answer by Cromlix(4381) About Me  (Show Source):
You can put this solution on YOUR website!
if it takes 4 men 9 hours to build a shed
It will take 6 men 4/6 * 9 hours
= 6 hours.