SOLUTION: It take 6 people 18 days to paint a wall. How long would it take for 9 people?
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: It take 6 people 18 days to paint a wall. How long would it take for 9 people?
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 778535
:
It take 6 people 18 days to paint a wall.
How long would it take for 9 people?
Answer by
solver91311(24713)
(
Show Source
):
You can
put this solution on YOUR website!
Hint: If it takes 18 days for 6 people, it would take 18 times 6 days for 1 person.