Question 774268: If it takes 6 men to do a job in 4 days how many days will it take 2 men
Answer by oscargut(2103) About Me  (Show Source):
You can put this solution on YOUR website!
6 men in 4 days
2 men in x days
where: 2x = 6(4) = 24
then x = 12
Answer: 12 days