Question 768474: Danielle can complete a project in twelve days and Mackenzie can do the same project in forty-eight days. Danielle worked on the project alone for four days before Mackenzie joined her. How many days did Mackenzie work on the project until it was done?
You can put this solution on YOUR website! Danielle's rate: job per day
MacKenzie's rate: job per day
Their combined rate: job per day
Basically r*d=j ----------- r is rate, d is days, j is job quantity
Danielle alone, 4 days.
MacKz joined Danielle, d days, unknown.
The project or job was done in 4+d days.
SOLVE FOR d.
To begin the symbolic solving, _____________________so actually finished solution.
8 days to finish with MacKenzie.
You can put this solution on YOUR website! Danielle can complete a project in twelve days and Mackenzie can do the same project in forty-eight days.
Danielle worked on the project alone for four days before Mackenzie joined her.
How many days did Mackenzie work on the project until it was done?
:
Let m = no. of days that M worked to complete the job with D
then
(m+4) = no. of days worked by D
;
Let the completed jobe = 1
:
the shared work equation + = 1
Clear the denominators, by multiplying by 48, resulting in:
4(m+4) + m = 48
4m + 16 + m = 48
5m = 48 - 16
m = 32/5
m = 6.4 days worked by M
:
:
We can confirm this by finding what fraction of the job each worked
the two fraction should add up to 1, (D worked 10.4 days)
10.4/12 = .867
6.4/48 = .133
---------------
total to: 1.00