SOLUTION: (1).
8 labourers do a work in 50 days . if the number of men are doubled , then in how many days will the same work be done ?
(2). 130 men dig a ttunnel in 170 days . how many me
Algebra ->
Average
-> SOLUTION: (1).
8 labourers do a work in 50 days . if the number of men are doubled , then in how many days will the same work be done ?
(2). 130 men dig a ttunnel in 170 days . how many me
Log On
Question 764402: (1).
8 labourers do a work in 50 days . if the number of men are doubled , then in how many days will the same work be done ?
(2). 130 men dig a ttunnel in 170 days . how many men will complete this task in 140 days ?
(3).
average of 5 numbers is 60 .sum of first two is 100 and last two is 160. find the fifth number?? Answer by josgarithmetic(39633) (Show Source):
You can put this solution on YOUR website! Find the rates of one man, for your questions #1 and #2. The question parts will then be simple to answer.
You have the describable form, N laborers do a job in D days. The rate for one man is then laborers does a job in days. Think how that works! The rate for one man in DAYS per JOB would then be .
Next you want to understand that when workers are working at the same time, then their individual rates are added.
In both #1 and #2, you will use where is the working rate, is time, and is how much or many jobs. In #1, the unknown variable to solve will be . In #2, the unknown variable to solve will be part of the rate ----- a whole number factor representing the rate for the group of unknown quantity of workers.