Question 764338: A gardener completes 5/8 of his landscaping job in 10 days. At this rate how many days will it take him to finish the job?
Answer by stanbon(75887) About Me  (Show Source):
You can put this solution on YOUR website!
A gardener completes 5/8 of his landscaping job in 10 days. At this rate how many days will it take him to finish the job?
---------------------------------
rate = (job done)/(hrs) = (5/8)/10 = (5/80) = 1/16 job/hr
----
Time to do the job is 16 hrs/job
=================================
Cheers,
Stan H.
==================