SOLUTION: If 7 men complete a job in 12 days. How many more men are required to complete that same job in 8 days/

Algebra ->  Human-and-algebraic-language -> SOLUTION: If 7 men complete a job in 12 days. How many more men are required to complete that same job in 8 days/      Log On


   



Question 763596: If 7 men complete a job in 12 days. How many more men are required to complete that same job in 8 days/
Answer by Cromlix(4381) About Me  (Show Source):
You can put this solution on YOUR website!
7 men to complete a job in 12 days
7 * 12 men to do the job in 1 day
(7 * 12)/8 to do the job in 8 days
10.5 men to do the job in 8 days
or 11 men.
So, 4 extra men are required.
Hope this helps
:-)