SOLUTION: An experienced worker can unload a truck in one hour forty minutes. When he works together with a trainee, they can unload the truck in one hour. How long would the trainee need to

Algebra ->  Rate-of-work-word-problems -> SOLUTION: An experienced worker can unload a truck in one hour forty minutes. When he works together with a trainee, they can unload the truck in one hour. How long would the trainee need to      Log On


   



Question 748790: An experienced worker can unload a truck in one hour forty minutes. When he works together with a trainee, they can unload the truck in one hour. How long would the trainee need to unload the truck if he works alone?
Answer by stanbon(75887) About Me  (Show Source):
You can put this solution on YOUR website!
An experienced worker can unload a truck in one hour forty minutes. When he works together with a trainee, they can unload the truck in one hour. How long would the trainee need to unload the truck if he works alone?
-----
exp worker rate = 1/100 job/min
together worker rate = 1/60 job/min
trainee worker rate = 1/x job/min
===============================================
Equation:
rate + rate = together rate
1/100 + 1/x = 1/60
-----
Multiply thru by 100*60x to get:
-----------------------------------
60x + (100*60) = 100x
-------
40x = 6000
x = 150 minutes (time for the trainee to do the job alone)
================
Cheers,
Stan H.
==================