SOLUTION: If it takes 3 people 4 hours to complete a task, how long will the same task take for 5 people?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: If it takes 3 people 4 hours to complete a task, how long will the same task take for 5 people?      Log On


   



Question 739669: If it takes 3 people 4 hours to complete a task, how long will the same task take for 5 people?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
3*4=12 man hours
5 people work for 12/5=2.4 hours also is 12 man hours