SOLUTION: It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if they work at the same rate?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if they work at the same rate?      Log On


   



Question 739013: It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if they work at the same rate?
Answer by lenny460(1073) About Me  (Show Source):
You can put this solution on YOUR website!
It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if they work at the same rate ?

4 men * 6 hours = 24 hours
7 men * x = 24 hours
7x = 24
x = 24/7
x = 3.42 hours
Answer:
7 men would take 3.42 hours to repair the road.





Lennox Obuong
Algebra Tutor
Nairobi, Kenya