SOLUTION: I it takes 7 people 8 days to dig a ditch, how many people would it take to dig it in 1/2 a day?
Algebra
->
Rate-of-work-word-problems
-> SOLUTION: I it takes 7 people 8 days to dig a ditch, how many people would it take to dig it in 1/2 a day?
Log On
Word Problems: Rate of work, PAINTING, Pool Filling
Word
Solvers
Solvers
Lessons
Lessons
Answers archive
Answers
Click here to see ALL problems on Rate-of-work-word-problems
Question 737569
:
I it takes 7 people 8 days to dig a ditch, how many people would it take to dig it in 1/2 a day?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
7*8 =56 man days
112 men to do it in half a day if they don't get in each others way