SOLUTION: How long will it take4 workers to complete a task, given that it takes 6 days for 6 workers to complete the same task?

Algebra ->  Customizable Word Problem Solvers  -> Travel -> SOLUTION: How long will it take4 workers to complete a task, given that it takes 6 days for 6 workers to complete the same task?       Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 736961: How long will it take4 workers to complete a task, given that it takes 6 days for 6 workers to complete the same task?


Answer by josmiceli(19441) About Me  (Show Source):
You can put this solution on YOUR website!
It takes 6 days for 6 workers to complete the task
It would take 1 of the workers 6 times as long to do the task, so
It takes 36 days for 1 worker to complete the task
-----------------------
4 times as many workers could do the task in 1/4 the time, so
It takes 9 days for 4 workers to complete the task