4 people can paint 5 walls in 39 minutes.
How many minutes will it take for 6 people to paint 9 walls?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
4*39=156 man minutes for 5 walls
156/5 man minutes per wall
156/5*9/6= 46.8 minutes