SOLUTION: Please help me solve this equation: It takes 4 men 16 hours to pave a footpath. How long would it take 3 men to pave the same area?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: Please help me solve this equation: It takes 4 men 16 hours to pave a footpath. How long would it take 3 men to pave the same area?      Log On


   



Question 731045: Please help me solve this equation: It takes 4 men 16 hours to pave a footpath. How long would it take 3 men to pave the same area?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
There is no equation to solve.
It is a rate of work word problem.
4*16=64 man hours are needed
It is assumed in this type problem that everyone works at the same rate.
64/3=21 1/3 hours for 3 men