SOLUTION: the time t required to do a certain job varies inversely as the number of people in working (assuming all work at the same rate) it takes 4 hours for 20 people working together to

Algebra ->  Customizable Word Problem Solvers  -> Misc -> SOLUTION: the time t required to do a certain job varies inversely as the number of people in working (assuming all work at the same rate) it takes 4 hours for 20 people working together to       Log On

Ad: Over 600 Algebra Word Problems at edhelper.com


   



Question 718680: the time t required to do a certain job varies inversely as the number of people in working (assuming all work at the same rate) it takes 4 hours for 20 people working together to wash and wax all the floors in a building how long would it take 25 people working together to complete the same job
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
the time t required to do a certain job varies inversely as the number of people in working (assuming all work at the same rate)
it takes 4 hours for 20 people working together to wash and wax all the floors in a building
Find the no. of man-hrs required to do the job
4 * 20 = 80 man-hrs
:
how long would it take 25 people working together to complete the same job
let t = time required with 25 people
25t = 80
t = 80/25
t = 3.2 hrs
:'
you can also do this with a inverse ratio relationship
t%2F4 = 20%2F25
cross multiply
25t = 4 *20
t = 80/25
t = 3.2 hrs