Question 709419:  Workers A and B, working together, can finish a job in 8 hours. If they work together for 6 hours after which Worker A leaves, then Worker B needs 9 more hours to finish the job. How long does it take Worker A to do the job alone? 
 Answer by ptaylor(2198)      (Show Source): 
You can  put this solution on YOUR website! Let x=amount of time needed for worker A to complete  the job working alone 
And y=amount of time needed for worker B to complete the job working alone 
Worker A works at the rate of 1/x of the job per hour 
Worker B works at the rate of 1/y of the job per hour 
Together they work at the rate of 1/8 of the job per hour, soooo 
1/x + 1/y = 1/8----------------eq1
 
If they work together for 6 hours, they complete 6*(1/8)=6/8=3/4 of the job leaving 1/4 of the job to be completed 
When worker A leaves, worker B completes 1/4 of the job in 9 hours, or 
9*(1/y)=1/4-----------eq2
 
We can simplify both equations: 
Eq1:  multiply each term by 8xy: 
8x+8y=xy----eq1a 
Eq2: multiply each term by 4y: 
36=y or  
y=36 hours ---time required for worker B working alone to complete the job 
substitute y=36 into eq1a: 
8x+8*36=36x 
28x=288 
x=10.29 hours---Time required for A working alone to complete the job
 
 
CK 
1/(10.29)+1/36=1/8
 
0.0972+0.028=0.125 
0.125~~~~0.125  OK
 
Hope this helps---ptaylor
 
 
 
  | 
 
  
 
 |   
 
 |   
 |  |