You can put this solution on YOUR website! If 10 workers can finish the work in 1 day,
Find how many man-days required to finish the job.
10 * 1 = 10 man-days to do the job
:
how about 8 workers? Please with solution.
let d = no. of days required when 8 men work
8d = 10
d = 10/8
d = 1 days