SOLUTION: 7 men can put a fence in 8 hours. if one man fall ill, how many overtime hours will the remaining men need to put up the same fence?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 7 men can put a fence in 8 hours. if one man fall ill, how many overtime hours will the remaining men need to put up the same fence?      Log On


   



Question 701834: 7 men can put a fence in 8 hours. if one man fall ill, how many overtime hours will the remaining men need to put up the same fence?
Answer by ptaylor(2198) About Me  (Show Source):
You can put this solution on YOUR website!
If 7 men can put up a fence in 8 hours, then 1 man can put up the fence in 7*8=56 hours. Therefore, it takes 56 man-hours to put up the fence.
Soooo, 6 men need 56/6=9 1/3 hours to put up the fence. This means that they work 1 1/3 overtime hours
Hope this helps---ptaylor