SOLUTION: Ten workers can paint a house in six days. Working at the same rate, how many days will it take for 2 workers to paint the house?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: Ten workers can paint a house in six days. Working at the same rate, how many days will it take for 2 workers to paint the house?
Log On
Question 681982: Ten workers can paint a house in six days. Working at the same rate, how many days will it take for 2 workers to paint the house? Answer by Alan3354(69443) (Show Source):
You can put this solution on YOUR website! Ten workers can paint a house in six days. Working at the same rate, how many days will it take for 2 workers to paint the house?
-----------
10*6 = 60 man-hours
---
60 m-h/2 m = 30 days