SOLUTION: 12 men can do a job in 8 days. If after 5 days,they are joined by 4 more men, how many more days would they take to finish the job
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 12 men can do a job in 8 days. If after 5 days,they are joined by 4 more men, how many more days would they take to finish the job
Log On
You can put this solution on YOUR website! 12 men can do a job in 8 days.
Find the number of man-days required to do the job
12*8 = 96 man-days
:
If after 5 days,they are joined by 4 more men, how many more days would they take to finish the job
:
let d = additional days required to complete the job
8(d+5) + 4d = 96
8d + 40 + 4d = 96
12d = 96 - 40
12d = 56
d = 56/12
d = 4 days to finish the job
:
:
:
See if that checks out, using decimals
8(4.67+5) + 4(4.66) =
77.36 + 18.68 = 96.04 ~ 96 man-hrs