Question 674348: If 7 guys take 8 days to build a trench, how many guys will it take to build the trench in 1/2 day? Found 2 solutions by ewatrrr, josmiceli:Answer by ewatrrr(24785) (Show Source):
You can put this solution on YOUR website! 7 guys take 8 days for 1 trench
It takes 8 times as may guys to do 1
trench in 1/8 of that time, or 1 day, so
It takes 56 guys 1 day to do 1 trench
To do it in 1/2 that time will take twice as many guys
112 guys can do 1 trench in 1/2 day