SOLUTION: Five workers can do 7 jobs in 3 days. How many days will it take 10 workers to do 14 jobs?

Algebra ->  Formulas -> SOLUTION: Five workers can do 7 jobs in 3 days. How many days will it take 10 workers to do 14 jobs?      Log On


   



Question 66497This question is from textbook Advanced mathematics
: Five workers can do 7 jobs in 3 days. How many days will it take 10 workers to do 14 jobs? This question is from textbook Advanced mathematics

Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
Five workers can do 7 jobs in 3 days. How many days will it take 10 workers to do 14 jobs?
:
Can we look at it this way? It takes (5*3) = 15 man/days to do 7 jobs
:
Let x = number of days to do 14 jobs; 10x man/days to do 14 jobs
:
%2810x%29%2F15 = 14%2F7
:
Cross multiply:
7(10x) = 15*14
70x = 210
x = 210/70
x = 3 days
:
10 men for 3 days = 30 man/days
:
Check, using man/days per job: 15/7 = 2.142857 per job
14 jobs would require: 2.142857*14 = 30 man/days