Question 646678:  A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A leaves, B and C continue for 20 days more days, after which B leaves. then C working for one-third longer each day completes the remaining work in 96 more days. If C had been working working at its own original rate then he would have completed the work in 222 days. How long would B take? 
 Answer by htmentor(1343)      (Show Source): 
You can  put this solution on YOUR website! Let a, b, c be the three work rates 
Working together, they can complete the job in 60 days: 
a + b + c = 1 job/60 d = 1/60 
After 10 days, the job is (1/60)*10 = 1/6 complete 
B and C working together for 20 days complete this much of the job: 20(b+c) 
Then C working alone completes the job in 96 days working 4/3 as much per day. 
So C completes this much of the job: 96c(4/3) = 128c 
C working alone can complete the job in 222 days, so c = 1/222 
Since after the first 10 days 5/6 of the job gets completed, we can write: 
5/6 = 128c + 20(b+c) 
5/6 = 128/222 + 20b + 20/222 
Simplifying gives 5/6 = 4/6 + 20b 
b = (1/6)/20 = 1/120 
So B can complete the job in 120 days 
  | 
 
  
 
 |   
 
 |