Question 628005: A person can finish his building work in 8days, but unfortunately while building every day he loses his 20% of work. inthat case how many days he can finish his building work?
Each day he does 1/8th of the job but then loses 20% of that 1/8.
Since 20% = 20/100 = 1/5, he loses 1/5th of 1/8th of the job.
1/5th of 1/8th is 1/40th. So each day he loses 1/40th of the job
out of that 1/8th that he did. So each day he completes
1/8 - 1/40 = 5/40 - 1/40 = 4/40 = 1/10th of the job.
So it will take him 10 days to finish the job.
Edwin