You can put this solution on YOUR website! 16 people finishes 2/3 of the job in 7 days, how many people can finish remaining job in 2 days
**
man-days required to finish 2/3 of the job=7*16=112
man-days required to finish remaining 1/3 of the job=112/2=56
people required to finish the job=56/2=28