SOLUTION: A can lay a lawn in 10 hours, B can lay a lawn in 8 hours.
What fraction of the lawn will A lay in one hour?
What fraction of the lawn will B lay in one hour?
What fraction of
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A can lay a lawn in 10 hours, B can lay a lawn in 8 hours.
What fraction of the lawn will A lay in one hour?
What fraction of the lawn will B lay in one hour?
What fraction of
Log On
Question 611032: A can lay a lawn in 10 hours, B can lay a lawn in 8 hours.
What fraction of the lawn will A lay in one hour?
What fraction of the lawn will B lay in one hour?
What fraction of the lawn would be laid in one hour working together?
How long would it take to lay the entire lawn? Answer by ewatrrr(24785) (Show Source):
Hi,
A can lay a lawn in 10 hours, B can lay a lawn in 8 hours.
What fraction of the lawn will A lay in one hour?
What fraction of the lawn will B lay in one hour?
What fraction of the lawn would be laid in one hour working together?
How long would it take to lay the entire lawn?
x = 40/9 = hrs