| Question 605828:  please help me to solve this problem. Thanks.
 If 30 laborers working 7 hours a day can finish a piece of work in 18 days, how many laborers working 6 hours a day can finish it in 30 days?
 Answer by josmiceli(19441)
      (Show Source): 
You can put this solution on YOUR website! (1) 30 laborers working 7 hours a day can finish a piece of work in 18 days (2) If they only work 1 hour a day, it will take them 7 times longer to finish, so
 (3) 30 laborers working 1 hour a day can finish a piece of work in 126 days
 (4) If they work 6 hours a day, It will take them 1/6 as long to finish
 (5) 30 laborers working 6 hours a day can finish a piece of work in 21 days
 (6) 7 times as many laborers can finish in 1/7 as many days, so
 (7) 210 laborers working 6 hours a day can finish a piece of work in 3 days
 (8) If they take 10 times longer to finish, they only need 1/10 as many laborers
 (9) 21 laborers working 6 hours a day can finish a piece of work in 30 days
 
 
 | 
  
 | 
 |