SOLUTION: It takes person A 4 hours less than person B to complete a certain task. Working together, both can complete the task in 8/3hours. How long does it take each person to complete the
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: It takes person A 4 hours less than person B to complete a certain task. Working together, both can complete the task in 8/3hours. How long does it take each person to complete the
Log On
Question 588034: It takes person A 4 hours less than person B to complete a certain task. Working together, both can complete the task in 8/3hours. How long does it take each person to complete the task working alone? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! Add their rates of working to get their
rate working together
Let ( 1 task ) / ( t hours ) = B's rate
given:
( 1 task ) / ( t - 4 hours ) = A's rate
Multiply both sides by
Use the quadratic formula ( ignore the (-) root )
It takes B 8 hrs to do the task alone
It takes A = 4 hrs to do the task alone
check answer:
OK