SOLUTION: The country's new paving machine can surface 1km of highway in 8 hours, whereas it takes the old one 12 hours. How long will it take them to surface 20 km of highway if they start
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: The country's new paving machine can surface 1km of highway in 8 hours, whereas it takes the old one 12 hours. How long will it take them to surface 20 km of highway if they start
Log On
Question 544460: The country's new paving machine can surface 1km of highway in 8 hours, whereas it takes the old one 12 hours. How long will it take them to surface 20 km of highway if they start at opposite ends and work day and night? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! the new one's rate of paving is km/hr
The old machine's rate is km/hr
----------
Add their rate off paving to get their rate of
paving together, , where is
their time in hours to pave km
---------
Multiply both sides by
It will take them 96 hrs