| Question 532457:  A group of 18 people can paint a house in 21 days.  If the house needs to be painted in 14 days, how many more people are required?    I figured out the rate of people per day, but then I get 12 or 16 people needed.  That doesn't make sense because you need more people to get the job done faster.  Help, please?
 Answer by lwsshak3(11628)
      (Show Source): 
You can put this solution on YOUR website! A group of 18 people can paint a house in 21 days. If the house needs to be painted in 14 days, how many more people are required? I figured out the rate of people per day, but then I get 12 or 16 people needed. That doesn't make sense because you need more people to get the job done faster. **
 Think in terms of man-days required to paint the house.
 18 people painting the house for 21 days=21*18=378 man-days
 If you need to paint the same house in 14 days, it would still require 378 man-days.
 So you need more men like 378/14=27 men
 27 men * 14 days =378 man-days
 ans:
 13 more people are required to paint the house in 14 days.
 | 
  
 | 
 |  |  |