SOLUTION: PLS help me on this word problem.. 18 workers can finish a job in 5 days.how many workers do they need to finish a job in 3 days?:)

Algebra ->  Rate-of-work-word-problems -> SOLUTION: PLS help me on this word problem.. 18 workers can finish a job in 5 days.how many workers do they need to finish a job in 3 days?:)      Log On


   



Question 512991: PLS help me on this word problem.. 18 workers can finish a job in 5 days.how many workers do they need to finish a job in 3 days?:)
Answer by nerdybill(7384) About Me  (Show Source):
You can put this solution on YOUR website!
Sorry, someone pointed out I made a mistake...
.
18 workers can finish a job in 5 days.how many workers do they need to finish a job in 3 days?
.
Applying ratios:
18/5 = x/3
cross multiplying
5x = 3*18
x = (3*18)/5
x = 10.8