Question 507764: It will take 24 men working 9 hours a day each to build a house in 45 days. Given that all men work at the same rate,
a. How nay days will 18 men take to build the same house if they work 8 hours a day ?
b. how many hours per day must 20 men work if the house is to be completed in 48 days ? Answer by lwsshak3(11628) (Show Source):
You can put this solution on YOUR website! It will take 24 men working 9 hours a day each to build a house in 45 days. Given that all men work at the same rate,
a. How many days will 18 men take to build the same house if they work 8 hours a day ?
b. how many hours per day must 20 men work if the house is to be completed in 48 days ?
**
Man-hours to build the house=24*9*45=9720
a. How many days will 18 men take to build the same house if they work 8 hours a day ?
let x=days to build the same house
18*8*x=9720
x=9720/(18*8)=67.5 days
..
b. how many hours per day must 20 men work if the house is to be completed in 48 days ?
let u = hours per day 20 men must work
20*u*48=9720
u=9720/(20*48)=10.125 hrs/day