| Question 470421:  The Acme Class Ring Company designs and sells two types of rings: the VIP and the SST. The company can produce up to 56 rings each day, using up to 140 total man-hours of labor. It takes 7 man-hours to make one VIP ring and 2 man-hours to make one SST ring. Let x represent the number of VIP rings, and let y represent the number of SST rings. Including the system inequalities  and , find the remaining inequalities that best describe this company's ring production.
 Answer by ankor@dixie-net.com(22740)
      (Show Source): 
You can put this solution on YOUR website! The Acme Class Ring Company designs and sells two types of rings: the VIP and the SST.
 The company can produce up to 56 rings each day, using up to 140 total man-hours of labor.
 It takes 7 man-hours to make one VIP ring and 2 man-hours to make one SST ring.
 Let x represent the number of VIP rings, and let y represent the number of SST rings.
 Including the system inequalities and, find the remaining inequalities that best describe this company's ring production.
 :
 No. of rings
 x + y =< 56
 :
 Labor:
 7x + 2y =< 140
 :
 x=>0
 y=>0
 | 
  
 | 
 |