Question 425487: If 6 men can do a peice of work in 14 days, how many men are needed to do work in 21 days?
Answer by Alan3354(69443) About Me  (Show Source):
You can put this solution on YOUR website!
6 men * 14 days = 84 man-days
M * 21 = 84
M = 4 men