Question 420060
:
8 workers can complete 2 projects in 9 days. How many workers are needed to complete 5 projects in 12 days?
Answer by
sudhanshu_kmr(1152)
(
Show Source
):
You can
put this solution on YOUR website!
for one project 9*8/2 = 36 man days is needed
so, for 5 projects, 36*5 = 180 man days
180/12 = 15
so, 15 workers are needed.