SOLUTION: 1) It took 24 workers working 10 hours per day for 24 days to complete a task. At this rate, how many days will it takes 60 workers to complete the same task working 8 hours per da
Algebra ->
Average
-> SOLUTION: 1) It took 24 workers working 10 hours per day for 24 days to complete a task. At this rate, how many days will it takes 60 workers to complete the same task working 8 hours per da
Log On
Question 409060: 1) It took 24 workers working 10 hours per day for 24 days to complete a task. At this rate, how many days will it takes 60 workers to complete the same task working 8 hours per day?
2)Five robots produce five automotive parts in five minutes, How many packages each containing one part could be made by ten robots in ten hours?
Thanks in advance. Answer by ankor@dixie-net.com(22740) (Show Source):
You can put this solution on YOUR website! 1) It took 24 workers working 10 hours per day for 24 days to complete a task.
:
Find the no. of man-hours required to complete this job
24 * 10 * 24 = 5760 man-hours
:
At this rate, how many days will it takes 60 workers to complete the same task working 8 hours per day?
:
let d = no. of days required to complete the job
60 * 8 * d = 5760
480d = 5760
d =
d = 12 days
;
;
2)Five robots produce five automotive parts in five minutes,
:
Find how many robot-minutes per part = 5 robot-minutes per part
:
How many packages each containing one part could be made by ten robots in ten hours? = 1200 parts
: