If 8 painters can paint the house in 6 hours, how long will it take 12 painters to paint the house?
Answer by
Fombitz(32388)
(
Show Source
):
You can
put this solution on YOUR website!
It takes 8*6=48 painter-hours to finish the job.
With 12 painters, it would take 48/12=4 hours.