SOLUTION: A painter knows that he can paint 3 houses in 5 weeks. At this rate how long should it take him to paint 14 houses?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: A painter knows that he can paint 3 houses in 5 weeks. At this rate how long should it take him to paint 14 houses?      Log On


   



Question 376669: A painter knows that he can paint 3 houses in 5 weeks. At this rate how long should it take him to paint 14 houses?
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
A painter knows that he can paint 3 houses in 5 weeks.
At this rate how long should it take him to paint 14 houses?
:
Let w = no. of weeks to paint 14 house
:
Use a ratio equation
3%2F14 = 5%2Fw
cross multiply
3w = 14*5
3w = 70
w = 70%2F3
w = 23.33 weeks