SOLUTION: It takes 9 people 9 days to finish a project if they work 9 hours a day. If only 8 people work only 8 hours a day, how long would it take?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: It takes 9 people 9 days to finish a project if they work 9 hours a day. If only 8 people work only 8 hours a day, how long would it take?
Log On
Question 358986: It takes 9 people 9 days to finish a project if they work 9 hours a day. If only 8 people work only 8 hours a day, how long would it take? Answer by robertb(5830) (Show Source):
You can put this solution on YOUR website! This is a problem on inverse variation. The no. of days D to finish the work is inversely proportional to the number of hours worked h and the number of people p working. Thus , where k is a proportionality constant. , so that .
Then hours.