You can
put this solution on YOUR website!
Hi,
Note: contractor A will cost $12,000 working alone to finish in 80 days
Finding the time it would take working together.

Multiplying thru with 80*100*x to clear the denominators
100x + 80x = 8000
180x = 8000
x = 44.44 hrs Time would meet deadline..
Cost:
150*44.44hr + 100*44.44hr = 6666.66 + 4444.44 = $11,111.17
Mix use of contractor A and contractor B would minimize the total cost (and meets deadline)