Question 358410
:
Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?
Answer by
mananth(16946)
(
Show Source
):
You can
put this solution on YOUR website!
6 people ----------- 8 days
8 people ------------?
indirect variation
6/8*8
= 6 days
...