SOLUTION: 60 men worked 12 days on a job. How many men would it take to complete the same job in 8 days?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 60 men worked 12 days on a job. How many men would it take to complete the same job in 8 days?      Log On


   



Question 351584: 60 men worked 12 days on a job. How many men would it take to complete the same job in 8 days?
Answer by nyc_function(2741) About Me  (Show Source):
You can put this solution on YOUR website!
Let m = the amount of men we are searching for

60/m = 12/8

12m = 60 * 8

12m = 480

m = 480/12

m = 40

So, 40 men can do the same job in 8 days.