60 men worked 12 days on a job. How many men would it take to complete the same job in 8 days?
Answer by
nyc_function(2741)
(
Show Source
):
You can
put this solution on YOUR website!
Let m = the amount of men we are searching for
60/m = 12/8
12m = 60 * 8
12m = 480
m = 480/12
m = 40