Question 350666: A pool takes 6 hours to fill and 9 hours to drain. If the drain is left off for 6 hours while the pool is being filled, how long did filling the pool take?
Answer by Fombitz(32388) About Me  (Show Source):
You can put this solution on YOUR website!
Rate*Time=Output
.
.
.
Let Z be the volume of the pool.
.
.
.
Filling rate: 6%2AR%5Bf%5D=Z
1. R%5Bf%5D=Z%2F6
Draining rate:9%2AR%5Bd%5D=Z
2. R%5Bd%5D=Z%2F9
.
.
.
Filling while the drain is open for 6 hrs: %28R%5Bf%5D-R%5Bd%5D%29%2A6=Z1
Find Z1.
Substituting from eq. 1 and eq. 2,
%28Z%2F6-Z%2F9%29%2A6=Z1
Z1=Z%281-2%2F3%29=Z%2F3
.
.
.
Z-Z%2F3=%282%2F3%29Z still needs to be added
Find that time, now the drain has been closed.
R%5Bf%5D%2At=%282%2F3%29Z
%28Z%2F6%29%2At=%282%2F3%29Z
+t=4+ hrs
.
.
.
Total time:T=6%2B4
highlight%28T=10+hrs%29