Question 341087:  Demand for residential electricity at 6:00 P.M. on the first Monday in October in Santa Theresa County is normally distributed with a mean of 4,905 MW (megawatts) and a standard deviation of 355 MW. Due to scheduled maintenance and unexpected system failures in a generating station the utility can supply a maximum of 5,200 MW at that time. What is the probability that the utility 
will have to purchase electricity from other utilities or allow brownouts?
 
So I have tried this: 
 
(5200-4905)/355 = 0.830986
 
I do not know if I have answered this question correctly. Please review and help me, if you can.
 
Thank you!! 
 Answer by stanbon(75887)      (Show Source): 
You can  put this solution on YOUR website! Demand for residential electricity at 6:00 P.M. on the first Monday in October in Santa Theresa County is normally distributed with a mean of 4,905 MW (megawatts) and a standard deviation of 355 MW.  
------------------------------------ 
Due to scheduled maintenance and unexpected system failures in a generating station the utility can supply a maximum of 5,200 MW at that time.  
----------------------- 
What is the probability that the utility will have to purchase electricity from other utilities or allow brownouts?  
So I have tried this:  
z(5200) = (5200-4905)/355 = 0.8310 
Note: You have found the z-value associated with 5200. 
----------------- 
You now need to find the probability that z is greater than 0.8310 
----------------- 
P(x > 5200) = P(z > 0.8310) = normalcdf(0.8310,100) = 0.2030 
---------------------- 
Cheers, 
Stan H.  
 
  | 
 
  
 
 |   
 
 |