SOLUTION: It takes 12 people 1 day to finish 1 job, how long would it take 8 people to finish the same job?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: It takes 12 people 1 day to finish 1 job, how long would it take 8 people to finish the same job?      Log On


   



Question 337095: It takes 12 people 1 day to finish 1 job, how long would it take 8 people to finish the same job?
Answer by Fombitz(32388) About Me  (Show Source):
You can put this solution on YOUR website!
(12/8) as long.
(12/8)(1)=1.5 days