Question 334404
:
10 people can do half of the work in 7 days ? how many days will take to do the same work by 5 men?
Answer by
mananth(16946)
(
Show Source
):
You can
put this solution on YOUR website!
10 people do the job in 14 days
5 people will do in how many days?
this is indirect proportion
..
5/10 * 14
=7 days
..