Question 320389: 6 men take 4 days to complete a part of a job. how many days will it take 8 men to do the same piece of work?
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
6 men take 4 days to complete a part of a job.
how many days will it take 8 men to do the same piece of work?
;
this is easy using man-days
:
6 * 4 = 24 man-days to complete job
:
Let d = no. of days for 8 men
8d = 24
d = 24/8
d = 3 days for 8 men to do it