Question 301370: The cost to rent a construction crane is $750 per day plus $250 per hour of use. What is the maximum number of hours the crane can be used each day if the rental cost is not to exceed $2500 per day? Answer by JBarnum(2146) (Show Source):
You can put this solution on YOUR website! H=hours total money minus the inital day fee divided by the amount per hours
so 7 hours is maximum