SOLUTION: The cost to rent a construction crane is $750 per day plus $250 per hour of use. What is the maximum number of hours the crane can be used each day if the rental cost is not to ex

Algebra ->  Equations -> SOLUTION: The cost to rent a construction crane is $750 per day plus $250 per hour of use. What is the maximum number of hours the crane can be used each day if the rental cost is not to ex      Log On


   



Question 301370: The cost to rent a construction crane is $750 per day plus $250 per hour of use. What is the maximum number of hours the crane can be used each day if the rental cost is not to exceed $2500 per day?
Answer by JBarnum(2146) About Me  (Show Source):
You can put this solution on YOUR website!
%282500-750%29%2F250=H H=hours total money minus the inital day fee divided by the amount per hours
1750%2F250=7
so 7 hours is maximum