Question 266865
:
if 12 men can build a wall in 8 days, in how many days will 16 men build the same wall at the same rate?
Answer by
josmiceli(19441)
(
Show Source
):
You can
put this solution on YOUR website!
If 12 men take 8 days, 1 man will take 12*8 = 96 days
If 1 man takes 96 days, 16 men will take
96/16 = 6 days