SOLUTION: A can have a piece of work done in 8 days, B can work three times faster than the A, C can work five times faster than A. How many days will they take to do the work together ?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A can have a piece of work done in 8 days, B can work three times faster than the A, C can work five times faster than A. How many days will they take to do the work together ?
Log On
Question 262698: A can have a piece of work done in 8 days, B can work three times faster than the A, C can work five times faster than A. How many days will they take to do the work together ?
(a) 3 days (b) 8/9 days (c) 4 days (d) can't say
You can put this solution on YOUR website! A can have a piece of work done in 8 days, B can work three times faster than the A, C can work five times faster than A. How many days will they take to do the work together ?
:
Let t = time required when working together
Let the completed job = 1
:
A shared work equation + + = 1
invert the dividing fraction and multiply, results + + = 1
multiply by 8 to get rid of the denominators, results
t + 3t + 5t = 8
9t = 8
t = days working together